CARIBOU – November 17, 2026 – The Maine Department of Transportation (MaineDOT) is providing an update on the Prestile Brook Bridge project on Route 164 in Caribou.
Supplier delays involving the fabrication and delivery of precast box sections have significantly affected the construction schedule. Due to the extent of the delays and the approaching winter season, the Route 164 closure and detour are now expected to remain in place throughout the winter and spring seasons.
MaineDOT and the contractor, McGillan Construction of Fort Fairfield, are making every effort to recover lost time and complete as much work as possible before winter weather limits construction activities. The contractor expects to begin placing the precast box sections by the end of November and will continue working as long as weather conditions permit. Construction activities will pause when freezing temperatures or snowfall prevent further progress.
McGillan Construction is expected to return to the site in the spring to resume construction and complete the remaining work, with the goal of having the entire project completed by early summer 2027.
The project involves replacing the existing Prestile Brook Bridge with a large culvert structure, improving fish and wildlife habitats, and reducing wildlife-vehicle collisions. The project is supported by a Federal Highway Administration (FHWA) Wildlife Crossings Pilot Program grant.
The original detour was established July 20, with an anticipated reopening date of November 20. Due to the revised schedule, motorists and pedestrians should continue following posted detour signs and use caution when traveling through the detour area. Message boards will continue to provide information about the closure.
MaineDOT appreciates the public's patience and understanding as the Department and contractor work to complete this project.